First, even if there is no written contract within the framework of the commercial relationship established between the parties, it should be stated that this contract pertains to force majeure and that, should a force majeure event occur, its legal consequences may apply to the parties. In this case, regardless of whether the parties have reached an agreement regarding force majeure, if a force majeure event occurs,
as a general rule, neither party may be held liable
for failing to perform any action or for a delay in performance due to force majeure;
therefore, the party is not liable
to the other party.²
However,
it is important to emphasize that the occurrence of a force majeure event does not always result in force majeure. This is because, in every case, there must be an appropriate causal link between the failure to perform the obligation and the occurrence of the force majeure event, rather than the performance of the obligation itself. In this context, the causal link is severed due to the failure to perform the obligation or the non-performance resulting from force majeure. On the other hand, the causal link resulting from force majeure
must be proven by the party affected by the force majeure event.
For example, in a sales contract, the seller or manufacturer faces a high likelihood of delay in delivering the product they have committed to deliver
due to potential delays in their operations, on the production line, or at customs
.
caused by the effects of the coronavirus. In this case, as long as it is proven that the delay resulted from the effects of the coronavirus, the party should be exempt from the contractual obligation arising from the performance of the obligation.
When examining the example in the paragraph above from the buyer’s perspective, the buyer’s claim that they cannot pay the purchase price or will experience a delay in paying the monetary debt due to the effects of the coronavirus should be evaluated more carefully, given the nature of the claim. Even if the buyer is always in a position to pay the debt, given that the effects of the coronavirus have been observed, it is becoming increasingly difficult to prove a proper causal link between the effects of the coronavirus and the failure to pay the assumed monetary debt. In such a case, for example, if banks remain closed for a period of time due to the effects of the coronavirus,
it is clear that a delay in payment during the period the banks are closed must be accepted.
Another example is when travel cannot be undertaken due to the effects of the coronavirus, as human-induced actions prevent performance; in such cases, it must be accepted that the party affected by force majeure will not be held liable for obligations arising from the contract due to failure to perform or a delay in performance.
Of course, when making an assessment in this context, the extent to which the coronavirus has impacted operations and
whether commercial activity in the affected region has come to a standstill must also be taken into account.
.
In conclusion, while the effects of the coronavirus are recognized as force majeure,
it must be determined whether there is an appropriate causal link between the force majeure event and the actions taken by the parties, the nature of the commercial
relationship, whether and to what extent the parties were affected by the force majeure, the nature of the parties’ actions, and all commercial matters and conditions—including the deadlines related to such actions and their start dates—must be taken into account, and each specific commercial relationship must be evaluated separately. This is because the impact of the coronavirus on each contract will be the same only when the various factors taken into account are identical
. Furthermore, the termination of a contract or the exercise of the right to withdraw from a contract in the event of force majeure
must be examined in each specific commercial relationship as needed.