Can the coronavirus pandemic constitute force majeure in the context of contractual relationships?
Since Turkish law does not include a definition or principles regarding force majeure, its scope of application is determined by legal doctrine and Supreme Court case law. Considering the relevant Supreme Court case law, it can be said that the existence of force majeure is assessed on a case-by-case basis and is interpreted narrowly, particularly with regard to merchants. However, within the framework of legal doctrine and Supreme Court decisions, the conditions required for an event to be recognized as force majeure can be listed as follows:
Force majeure must have occurred beyond the parties’ control;
it must have been unforeseeable at the time the legal relationship was established, or, even if foreseeable, its concrete impact must have been too great to predict;
despite all precautions, the force majeure must have rendered performance of the contract impossible and this could not have been prevented; and
the relevant event must have been specified as a force majeure event in the contract;
In addition to these basic criteria, the Supreme Court also considers factors such as whether the event alleged to constitute force majeure has a nationwide impact, its effect on similar legal relationships, and whether the parties are merchants.
Under Article 136 of the Turkish Code of Obligations (“TBK”), if one of the parties is unable to perform its obligation due to a circumstance such as force majeure, the provisions regarding subsequent impossibility of performance set forth in that article apply. According to this provision, if performance of the obligation becomes impossible due to reasons for which the debtor cannot be held liable, the obligation is extinguished by the statute of limitations. In such a case, there is no breach of contract.
.
As of today, there is no official statement, announcement, or notification indicating that the coronavirus constitutes a force majeure event in Turkey, nor is there a Supreme Court ruling on the matter. However, it must be acknowledged that the coronavirus is spreading at a more unpredictable rate worldwide compared to other pandemics, such as swine flu and avian flu, which have been the subject of recent Supreme Court decisions.
For this reason, it may be considered a force majeure event, particularly for companies and individuals engaged in commercial relations with countries heavily affected by the outbreak, such as China, Iran, South Korea, and Italy. However, as noted above, the Supreme Court bases its decisions on force majeure assessments on specific cases; the circumstances of the event and the terms of the contract between the parties largely shape the Supreme Court’s assessment. In particular, the Supreme Court appears to place great importance on how force majeure is defined in the contract and what events it covers, especially when dealing with merchants who are expected to exercise due diligence in all circumstances.
If it is determined that the effects of the coronavirus have not reached a level constituting force majeure (Tbk 138), assessing whether it is possible to request an adjustment from the court under this provision to maintain a sound commercial relationship may also be one of the options available.